Granby is requesting voters approve bonding for a major expansion of the town-owned sewer system. Granby officials appear to have neglected the design limitations of the pollution control plant in Simsbury, which needs to process this proposed large sewerage flow increase. Did Granby consult with Simsbury’s Water Pollution Control Authority on this matter? Granby has rights to send sewerage to Simsbury’s treatment facility through a usage agreement, but it does not own title to any portion of the plant.
The original sewerage contract with Simsbury was dated in 1979, signed in 1981 and amended in 2002. In 1981 a letter was included in order to provide several lots located in Granby near the Simsbury border to directly connect to Simsbury’s gravity flow piping system. All other flows from Granby are required to go to Simsbury’s Wolcott Street pump station, located near the airport. The capacity of Wolcott pump was not described by Granby’s consultant, Tighe and Bond, in its 2024 report. Nor did the consultant identify any current flow limitations with the Wolcott pump. This omission raises the question of the adequacy of the consultant’s report. The Wolcott pump station, as a minimum, would require debottlenecking before Granby can increase sewage flow.
The 2002 amendment was primarily intended for sharing costs associated with financing a capacity and environmental upgrade to the treatment plant. Under the agreement, Granby’s share of the costs associated with plant expansion were at a rate of 9.2 percent. The amendment is not clear if the 9.2 percent applies only to Granby’s costs, or additionally to a flow allotment of the upgraded 3.84 million gallon per day plant. In 2002 no specific reference is made as to extending the 20-year contract term. Assuming such an extension is implied, then the contract with Simsbury expired in 2022, and there is no evidence available that Granby extended the agreement.
Granby’s “Sewer Use and Reserve Policy” implies rights to send Simsbury 353,280 gallons per day. Not included in that number is 4,000 gallons per day from town septic systems. By contrast Simsbury’s data indicates Granby’s daily average limit for total transfer is 300,000 gallons per day. The only documented flow numbers date back to the 1979 contract wherein the deliverable average flow is 250,000 gallons and not to exceed 750,000 gallons per day. Furthermore, under Section I.3. Granby is required to halt connections if flows exceed 95 percent of the average limit over a 90-day period.
Granby wants to rebuild its pumping stations to a full build-out of the sewer zone capacity. The projected future peak flow rate would consume 40 percent of the current plant treatment capability. The town does not have the unilateral rights to increase the sewerage treatment plant capacity. Any plant expansion would be difficult and costly. The discharge permit into the Farmington River would most likely trigger a sensitive river condition status, require an upgrade to tertiary treatment controls for the entire plant and take a decade to complete.