Granby Center Road Construction Status

Print More

The contractor plans to continue granite curb installation and pave the widened shoulders of the road during late October and first weeks of November. It is also expected that sidewalks and ramps will be completed this fall, weather permitting. After this work is complete, the contractor will work to stabilize the area and winterize the project before shutting down for the winter. It should be noted that road paving will not be complete this year before the shut-down.